Construction Update
Urbana Irene
Block A – Fourth floor roof slab shuttering work in progress.
Block B – Sixth floor roof slab shuttering and second floor block work in progress.
Block C – Internal plastering completed and external plastering nearing completion.
Covai @ Tapovan Solace
Fourth floor roof slab is completed on the 1 BHK wing.
Fourth floor slab pore on the portico side work in progress.
Covai Ultra
Villa No 05 – Ground floor roof slab shuttering work in progress.
Villa No 12 – Ground floor roof slab shuttering work in progress.
Villa No 16 – First floor rood shuttering work in progress.
Villas No 18 – Ground floor roof slab shuttering work in progress.
Villa No 20 – Ground floor roof slab shuttering work in progress.
Villa No 23 – First floor roof completed.
Villas No 40 – First floor lintel brick work in progress.
Villa No 43 – Plastering work in progress.
Villa No 59 – Ground floor roof slab shuttering work in progress.